iMechE UAS Challenge 

Led Gryphon Arrows — 15+ people — to design and build an autonomous fixed-wing aircraft for IMechE’s international competition: GPS waypoint navigation and precision agricultural delivery within ±2 m, under a hard 10 kg limit.

Role
Project Manager
Organisation
University of Leeds
Period
October 2025 – June 2026
The Gryphon Arrows team badge: an eagle’s head in profile over a crossed arrow.
Gryphon ArrowsUniversity of Leeds · iMechE UAS Challenge 2025–26
Walkthrough
View

The team’s own SolidWorks assembly — 176 solids in ten subsystems, tessellated for the browser. Step through them and the rest drops to a ghost, so you can see inside the wing without losing the aeroplane.

AssembledAircraftTwo metres of span, under a 10 kg all-up limit.
  • iMechE UAS airframe — key figures
  • 2.0 mWingspan · built-up wing
  • 10 kgCompetition all-up limit
  • 2 × 11 inWing-mounted propulsion
  • Elevator + rudderConventional empennage

Evidence

  • 15+Team ledthree sub-teams
  • 10 kgMass limitcompetition
  • ±2 mDelivery accuracyGPS waypoint
  • £1,300+Budget managed
  • £1,000Sponsorship secured

Case study

01

The problem

  • IMechE sets a fixed rule set and a hard 10 kg all-up mass limit, and the delivery has to land within ±2 m of a GPS waypoint.
  • A mass limit is the one number every sub-team has to negotiate against every other.
02

The design

  • Three sub-teams — mechanical, electrical, software — working to one mass ledger.
  • GPS waypoint navigation with precision agricultural delivery.
03

What I did

  • Project manager for Gryphon Arrows — 15+ people across three sub-teams.
  • Held the mass budget and the schedule across all three sub-teams.
  • Managed £1,300+ of budget and secured £1,000 in sponsorship.
04

How it was tested

  • In progress — the competition runs to June 2026.
05

Result

  • Ongoing. The airframe above is the team’s own assembly, not a stand-in: 176 solids, tessellated from the SolidWorks build.

The team is Gryphon Arrows, the University of Leeds entry to the competition: fifteen people across mechanical, electrical and software, working to one rule set and a hard 10 kg all-up limit. I managed a £1,300+ budget and secured £1,000 in sponsorship.

A mass limit is the most useful constraint a project manager can be handed, because it is the one number every sub-team has to negotiate against every other. Structure wants material, propulsion wants margin, and the payload wants both. I held the ledger.

Plan-view schematic of a GPS waypoint route ending at a delivery point, with a circular tolerance envelope of plus or minus 2 metres around it.WP 1WP 2±2 mDELIVERY POINT04 m
Fig. P6 — Delivery accuracy envelope, ±2 m about the waypoint.

In progress — the competition runs to June 2026. The model above is the team’s working assembly and will move as the design does.